St. John’s Medical Center Modernization Program

Westlake, Ohio


At A Glance

stopwatch 2013

office Healthcare/Medical

highvolume Acoustical

usergroup Building Information Systems

building Exterior Insulation and Finish

clock Integrated Project Delivery

building Metal Framing and Drywall

paintroller Painting

calculator Pre-Construction Services

star Specialty Services

flame Spray On Fireproofing

OCP was selected in the Design Development phase and provided full  target cost estimates of the project.  The IPD team originally came in 8% over budget but worked together, and with some innovated value management, brought the target cost estimate to 5% below budget. OCP came approximately 8% under our target cost estimate and the team was able to complete project 4 months ahead of schedule.  OCP has provided BIM assistance to the project as requested by the Design Group.