St. John's Medical Center Modernization Program
Westlake, OH
At A Glance
- Date of Completion: 2013
- Market: Healthcare
- Clients
- Architect: Array HFS
- General Contractor: Donley's Inc.
- Scope of Work
- Pre-Construction Services, Building Information Systems, Lean Construction, Total Station, Acoustical, Exterior Insulation & Finish, Metal Framing & Drywall, Painting, Spray Foam Insulation, Specialty Services
OCP was selected in the Design Development phase and provided full target cost estimates of the project. The IPD team originally came in 8% over budget but worked together, and with some innovated value management, brought the target cost estimate to 5% below budget. OCP came approximately 8% under our target cost estimate and the team was able to complete project 4 months ahead of schedule. OCP has provided BIM assistance to the project as requested by the Design Group.